Record a team stoppage

2 min read

Equipment shutdowns allow recording the periods during which an asset is out of service.

The record can be made independently from Equipment Stoppages or directly from a work order when the stoppage is related to a maintenance intervention.

Register a stop from Equipment Stops

  1. Go to Operations > Equipment Stoppages .
  1. Select Create .
  1. Select the affected asset.
  1. Report the relevant information regarding the arrest.
  1. Indicate whether the stop is scheduled or unscheduled.
  1. Save the record.

[IMAGE: Screen Operation > Equipment Stops > Create showing the main data of a new stop]

Complete the stop details

When recording an equipment stoppage, complete the information corresponding to the stoppage.

Teams

Select one or more pieces of equipment affected by the shutdown.

Date from

Indicate the date and time the arrest began.

Date until

Indicate the date and time the stop ends.

Informant

Select the user who reports or records the arrest.

Scheduled stop

Enable this option when the stop has been previously scheduled.

Keep it disabled when it corresponds to an unscheduled stop.

Reason for stop

Select the reason corresponding to the equipment stoppage.

Grades

Record observations or additional information related to the stop.

[IMAGE: Create Equipment Stop form showing Equipment, Start Date, End Date, Informant, Scheduled Stop, Stop Reason and Notes]

Register a stop from a work order

When the arrest is related to an intervention, it can also be recorded directly from the work order.

  1. Go to Operations > Work Orders .
  1. Locate the corresponding order.
  1. Select Equipment Stop .
  1. Complete the arrest details.
  1. Incorporate other equipment when it is affected by the same shutdown.
  1. Save the record.

[IMAGE: Equipment Stop option from a work order showing the asset and stop information]

📌 Registering the stop from a work order allows the stop to be linked to the corresponding maintenance intervention.

Close a stop

When the equipment becomes available again, complete the stop closure to record the completion of the stop.

Once closed, the stop no longer appears as active and its information becomes available for historical analysis and maintenance indicators.

Related questions