Create a date-based activity

2 min read

Date-based activities allow you to generate one or more plans for a specific date, without needing to come from a previous job request or program.

They can be used to plan a general maintenance task or a reading task.

Create a date-based activity

  1. Go to Operations > Planning .
  1. Select Create .
  1. Define whether the activity corresponds to a reading task using the option "Is it a Reading task?" .
  1. Complete the corresponding information.
  1. Save the record.

It is also possible to start the creation from the calendar view, directly selecting the day on which you want to schedule the activity.

[IMAGE: Screen Operations > Planning > Create showing the form for a date-based activity]

Create a date-based activity

When the "Is this a Reading assignment?" option is disabled, complete the general information about the activity.

Asset type

Select the type of asset on which the task will be performed.

Asset

Select one or more assets corresponding to the indicated type.

Component

Select a component when the task must be performed on a specific part of the asset. This information is not required.

Task

Select the task that should be performed on the chosen assets.

📌 It is not mandatory for an asset to have components in order to plan a task. The task can be directly associated with the asset.

Create an activity for the reading date

When the activity aims to record a reading, enable the option "Is this a Reading assignment?" .

When activating this option, complete the following information:

Asset

Select the asset on which the reading will be recorded.

Meter

Select the meter corresponding to the value that should be recorded.

Component

Select the associated component when applicable.

Task

Select the reading task that should be executed.

[IMAGE: Activity to Date form with the "Is this a Reading task?" option enabled, showing Asset, Meter, Component, and Task]

Once the activity has been created, the generated plans are available in Operations > Plans to continue managing them.

From there it is possible to allocate resources, modify the planning and generate or assign tasks to a work order.