The programs allow you to define maintenance plans to establish what tasks should be performed on certain assets and under what conditions their planning should be generated.
A single program can contain different maintenance details, each with its own assets, tasks, and triggers.
Create a program
- Go to Operations > Programs .
- Select Create .
- Complete the program name.
- Select New to add a detail.
- Complete the details information.
- Save the record.
[IMAGE: Screenshot Operation > Programs > Create showing the program name and the New option]
Complete the program details
General program information
Guy
Select the type that corresponds to the program.
Name
Enter a name that allows the program to be identified and differentiated.
Managers
Select the users who will be associated with the program when appropriate.
Generate automatic work order
Enable Automatic Work Order Generation when it is required that the schedules generated by the program automatically create their work orders.
[IMAGE: Create program header showing Type, Name, Responsible Parties and Generate automatic OT]
Add details to the planning
A program may contain one or more planning details.
To add a new detail, select the + button located in the grid and complete the corresponding information.
Asset
Select the asset on which the task will be performed.
Component
Select a component when the task must be performed on a specific part of the asset's structure. This information is not required.
Task
Select the task that should be performed on the indicated asset or component.
Activator
Define the condition that will determine when to generate the task plan.
It is possible to incorporate several details within the same program, each with its own configuration of asset, component, task, and trigger.
The available types are:
- For a time .
- By frequency .
- By time and frequency .
- By double frequency .
- Per event .
- Predefined days.
[IMAGE: Program details grid showing the + button and the columns Active, Component, Task, and Trigger]
Once created, the program is configured with the defined assets, tasks, and triggers.
When the conditions established for each trigger are met, the corresponding plans are generated to continue their management from Operations > Planning .